How-to · UK domestic

How to wire a Solis hybrid inverter with battery

The Solis RHI and S5/S6 hybrid inverters sit at the centre of a solar-plus-storage system: they take DC from the panels, talk to the grid, and charge or discharge a battery as needed. Getting the wiring sequence and CT clamp placement right matters. A backwards CT reading alone will cause the inverter to export battery power when it should be storing, running up your electricity bill instead of cutting it.

Helpful video reference. We use Ben Curry of "Solis Hybrid Inverter and Puredrive battery installation" (Electrical Innovations Ltd, Derby) as the video reference here. Ben is a UK MCS-accredited installer and the walkthrough is used by Solis as official support material for the RHI and S5-EH1P series with Puredrive batteries.

Before you start. Isolate at the consumer unit. PV strings produce voltage in daylight even with the inverter switched off — always cover the panels or open the DC isolator before touching any DC terminals. Electrical work on a grid-tied solar system is notifiable under Part P and must be done by a competent person.

1. Plan the installation and get DNO approval

Before anything is wired, you need to know which notification route applies. G98 covers single-phase generation up to 3.68 kW export — most domestic Solis hybrid installs with existing solar fall here. G99 applies if you are above that threshold or if the DNO requests it. Submit the notification to your Distribution Network Operator before you energise the system; the DNO has up to 20 working days to object under G99, though G98 is typically automatic.

Also check the consumer unit has a spare 32A MCB or RCBO slot and that the existing cable sizes and main fuse can handle the additional load.

2. Mount the inverter

Solis specifies a solid indoor wall, away from direct sunlight and moisture. Leave the clearances in the installation manual: typically 200 mm above and below, 150 mm each side. Under BS 7671:2018+A4:2026 (the 18th Edition with Amendment 4, effective April 2026), battery storage equipment must not be installed in escape routes, stairwells, hallways, sleeping rooms or under-stairs cupboards. A garage wall or a utility room are both fine choices.

Use the supplied wall bracket, check it is level, and fix into solid masonry or through a stud into timber. The inverter is not light — a 5 kW Solis S5 weighs around 14 kg without a battery.

3. Connect the DC solar string input

Use the Solis MC4 tool (or a compatible MC4 crimp) to terminate the connectors on the PV string cables. Before connecting to the inverter, measure the string open-circuit voltage with a multimeter. It must be within the inverter's rated input range — for a typical Solis 5 kW S5-EH1P, the max input VOC is 500 V. Connect only when confirmed safe.

Keep DC+ and DC– labelled clearly at both ends. MC4 connectors are polarised and should not go on wrong, but labelling prevents confusion during commissioning and any future maintenance.

4. Wire the AC grid connection

Run 10 mm² twin-and-earth on a dedicated 32A Type C MCB or RCBO from the consumer unit to the inverter AC input terminals (L, N, PE). The cable must be suitably rated for its full route length and clipping method. Fit an accessible AC isolator adjacent to the inverter so the system can be isolated locally without returning to the consumer unit.

The AC terminals on most Solis hybrid inverters are inside the bottom of the casing. Refer to the terminal diagram in the manual for your specific model — the RHI and S5/S6 series differ slightly in layout.

5. Connect the battery

Fit the BMS communication cable first, before any DC power cables. Puredrive Energy batteries communicate via CAN bus; Pylontech units use RS485. The correct cable type is specified in the battery manual and must match the port on the Solis inverter. Getting the protocol wrong means the inverter cannot read state of charge, so it cannot manage the battery correctly.

Once communication is confirmed, connect the DC power cables per the battery manual's sequence — typically positive first, then negative. Torque the terminals to the values given in the manual. Confirm compatibility with your specific Solis model number before purchase: not every Solis variant supports every battery brand.

6. Install the CT clamp and energy meter

Clip the CT sensor onto the live tail between the electricity meter and the main consumer unit, with the printed arrow facing toward the consumer unit. This orientation tells the inverter whether the property is currently importing from or exporting to the grid.

An incorrectly oriented CT inverts the reading, so the inverter discharges the battery into the grid when it should be storing solar generation. It is a common commissioning error. If the system seems to drain the battery during sunny periods rather than fill it, the CT direction is usually the culprit.

7. Commission and test

Power up in sequence: AC supply first, then battery, then DC strings last. The Solis display should show correct grid voltage and frequency (230 V, 50 Hz). Open the SolisCloud app, pair the inverter via the Wi-Fi dongle, and configure battery type, usable capacity, minimum state of charge and any export limit the DNO has specified.

Check that the CT reading in the app matches actual import or export (a plug-in kettle is an easy test load). Once everything reads correctly, complete and submit the G98 or G99 notification form to the DNO. Keep a copy. Issue an Electrical Installation Certificate or Minor Works Certificate as appropriate.

Stop and call an electrician if: the consumer unit has no spare way, the existing PV system uses a different inverter brand and the wiring is unfamiliar, the battery BMS protocol is not listed as compatible in the Solis manual, or any error code on the inverter display is not resolved by the fault guide in the manual.

When to call us

Richard covers solar battery installations across east Kent, including battery retrofits to existing solar systems. If you have panels already and want to add a Solis hybrid inverter and battery, he can assess the existing installation, handle the DNO notification and issue the certificates.

Need a solar battery installer in east Kent?

Richard handles the full job: consumer unit assessment, inverter wiring, battery connection, CT clamp, DNO notification and certification.

Contact Richard

Related pages