Helpful video reference. We use BHC Distributors UK's walkthrough "Intro to the NEW Fronius GEN24 Plus & BYD Battery-Box in partnership with BHC Distributors (UK)" as the video reference here. BHC Distributors are a UK-based electrical wholesale distributor and produced this guide in partnership with Fronius UK Ltd, covering installation and commissioning for the GEN24 Plus with BYD Battery-Box.
1. Assess the site and get DNO approval
Start at the consumer unit. You need a spare 32A way for a dedicated radial circuit, and you need to know whether the installation falls under G98 or G99. The GEN24 Plus 3.0 kW and 4.0 kW models are G98-eligible for single-phase export up to 3.68 kW; the 5.0 kW and 6.0 kW models typically require a G99 application, which takes longer. Notify the DNO before the system is energised.
Also check the main fuse rating. A 60A or 80A main fuse in an older property may limit what can be added without an upgrade. If in doubt, call the DNO before work starts.
2. Mount the inverter
Fix the GEN24 Plus wall bracket to a solid indoor wall, ideally in a garage or utility room. Fronius specifies minimum clearances: 300 mm to the left and right of the inverter, 400 mm above and below. Leave enough room to open the cover and reach all cable glands.
Under BS 7671:2018+A4:2026 Section 722, battery storage systems must not be installed in lofts, under-stairs cupboards, bedrooms or on escape routes. The inverter and the BYD battery cabinet should both be in a suitable location before any cable work begins.
3. Connect the DC solar input
The GEN24 Plus has two independent MPPT inputs (string 1 and string 2), which allows two separate panel strings to run at different orientations without losing efficiency. Terminate the PV string cables using the MC4 connectors supplied. Before closing the DC isolator, verify that each string's open-circuit voltage is within the inverter's rated input range (typically up to 800 V DC for the GEN24 Plus).
Keep DC+ and DC– cables labelled. A reversal will trigger a fault immediately on power-up and can damage the inverter.
4. Wire the AC grid connection
Run 10 mm² twin-and-earth from a dedicated 32A Type C MCB or RCBO in the consumer unit to the inverter AC terminals (L, N, PE). Include an accessible AC isolator adjacent to the inverter so the grid supply can be disconnected without returning to the consumer unit.
The GEN24 Plus includes integrated arc-fault detection, which is a requirement under BS 7671:2018+A4:2026 for new solar PV installations. A metal consumer unit enclosure is preferred because it provides a degree of arc containment, though the GEN24 Plus's internal detection works with plastic enclosures too.
5. Install and wire the BYD Battery-Box
Mount the BYD HVM or HVS cabinet on a solid wall, following BYD's installation manual for fixing requirements. Under the new BS 7671 rules, maintain at least 2 m clearance from escape routes and from combustible materials (Section 722). Do not place the battery in a loft or under stairs.
Connect the DC power cables between the GEN24 Plus battery terminals and the BYD cabinet first, with the battery in a discharged state if possible. Then connect the CAN communication cable to the GEN24 Plus CAN port. This BMS link is what tells the inverter the battery's state of charge, cell temperatures and charge limits.
6. Wire the Fronius Smart Meter (EM240)
The Fronius Smart Meter is not optional. The GEN24 Plus will not commission without an energy meter providing the import/export reading, and without it, export limitation and time-of-use charging will not work.
Fit the EM240 to a DIN rail inside the consumer unit or in an adjacent enclosure. Clip the two CT sensors onto the meter tails between the meter and the main consumer unit, with the arrows facing toward the consumer unit. Run the RS485 Modbus cable from the EM240 to the Modbus port on the GEN24 Plus. The polarity of the CT sensors matters: a reversed CT inverts the import/export reading and causes the inverter to discharge the battery into the grid unintentionally.
7. Commission via Solar.web and submit G98
Power up in the correct sequence: BYD batteries first, then AC supply, then the DC strings (by closing the string DC isolators). The GEN24 Plus display should show the MPPT input voltage rising as the panels come online.
Open the Fronius Solar.web portal or the Solar.web app on a smartphone. Run through the setup wizard: set battery type (BYD), capacity, minimum state of charge, export limit and any smart charging schedules (such as off-peak charging from an Octopus Agile or Flux tariff). The EM240 Modbus reading should show a positive import value when the property is drawing from the grid and a positive export when the solar is generating above consumption.
Once commissioning is complete, download and complete the G98 or G99 notification form for the DNO, and issue the Electrical Installation Certificate.
When to call us
Hybrid inverter installations involve AC wiring, DC wiring, BMS commissioning and DNO paperwork. Richard covers solar battery and hybrid inverter installations across east Kent, handling everything from the initial consumer unit assessment through to Solar.web commissioning and the completed G98 submission.