How to submit a G98 or G99 DNO notification for solar panels

Every solar PV and battery storage installation that can export electricity must be notified to the Distribution Network Operator. In most cases the MCS-certified installer handles this, but knowing what the process involves helps you check the paperwork is correct and file the acknowledgement safely.

Helpful video reference. NXTGEN Energy Limited, an MCS-certified solar installer based in Essex and operating across Kent and London, explains the DNO application process in their video "Understanding DNO Applications for Solar Panels with NXTGEN Energy - Your MCS Certified PV Installer". Worth watching to understand what your installer is doing on your behalf and why the paperwork matters.

Before you start. G98 and G99 notifications must be submitted by or on behalf of the MCS-certified installer. You cannot self-certify a solar PV installation under Part P without MCS accreditation. If your installer has not sent you a notification reference or acknowledgement within six weeks of commissioning, chase them directly - it is their legal obligation under the Engineering Recommendation, not yours.

1. Confirm which form applies to your system

The threshold that separates G98 from G99 is the export capacity of your system, measured in kW per phase.

Your installer will know which route applies. If the system has a 4 kW or larger inverter, or if battery storage is included, ask them explicitly whether they are following the G98 or G99 route and when they expect to submit.

2. Find your DNO and its online portal

The UK has six major Distribution Network Operators. East Kent, including Sandwich, is served by UK Power Networks (UKPN). If your property is elsewhere, check your electricity bill or use the Energy Networks Association postcode tool to confirm your DNO.

Each DNO runs its own online portal for G98 notifications and G99 applications. UKPN's portal is at connections.ukpowernetworks.co.uk. Your installer will register and submit there. As the homeowner you do not need a portal account, but you should ask for the submission reference number and the acknowledgement document once it arrives.

3. Gather what the form requires

The installer needs the following to complete either a G98 notification or G99 application:

As the homeowner, your job is to make the MPAN available and to confirm the installation address. Everything else the installer prepares.

4. Submit the notification or application

For a G98 notification, the installer logs into the DNO portal, selects the G98 route, enters the system details and uploads supporting documents. The portal issues a reference number immediately, and the DNO sends a formal acknowledgement within a few working days. The notification must be submitted within 28 days of first energising the system.

For a G99 application, the sequence is reversed: the installer submits before installation begins, the DNO reviews the application (up to 45 working days by statute, often faster), and only then can the system be connected. If the DNO requires a modification to the protection settings or inverter configuration, the installer addresses that before commissioning.

Some DNOs have been slow to process G99 applications. If you are waiting for approval and the installer is pressing for a commissioning date, ask them whether a G98 route is permissible for your system size or whether there is an accelerated approval process.

5. Receive and file the acknowledgement

Once submitted and accepted, the DNO issues an acknowledgement document. For G98 this is typically a reference number and confirmation email. For G99 it is a formal letter or PDF confirming approval and any conditions.

File this document alongside your MCS certificate and the Electrical Installation Certificate (EIC) from the installer. You will need it in three situations:

Check this before signing off: ask your installer for the DNO notification reference number or G99 acceptance letter. If they cannot provide one within six weeks of commissioning, contact your DNO directly with your MPAN and the installation date. Unnotified systems are a risk at sale and may affect your SEG payments.

When to call us

Richard does not submit G98 or G99 notifications as a standalone service, but if you are getting solar panels or a battery storage system fitted and need the electrical supply assessment, consumer unit check or DC isolator wiring done to MCS standards, get in touch. We are also happy to look over the paperwork if something does not look right.